File #:
|
Details 2024-077
Version:
1
|
Name:
|
|
Type:
|
CN - Certificate of Need
|
Status:
|
Agenda Ready
|
On agenda:
|
5/2/2024
|
Final action:
|
|
Title:
|
** E002/CN-22-131; Northern States Power Co. d/b/a Xcel
E002/TL-22-132 Energy
In the Matter of the Application of Northern States Power Co. d/b/a Xcel Energy for a Certificate of Need and Route Permit for the Minnesota Energy Connection Project in Sherburne, Stearns, Kandiyohi, Wright, Meeker, Chippewa, Yellow Medicine, Renville, Redwood, and Lyon counties in Minnesota.
1. What action should the Commission take concerning route alternatives to be evaluated in the environmental impact statement?
2. What actions, if any, should the Commission take concerning other procedural items? (PUC: Ek)
|
Attachments:
|
1. PUC Order 6-28-22, 2. Xcel Filing Letter 3-9-23, 3. Xcel Summary of Filing 3-9-23, 4. Xcel Application Text 3-9-23, 5. Xcel Appendices Part 1 of 2 3-9-23, 6. Xcel Appendices Part 2 of 2 3-9-23, 7. PUC Order 5-2-23, 8. Xcel Revised Application Filing Letter 5-18-23, 9. Xcel Revised Application Application Text 5-18-23, 10. Xcel Revised Application Appendices Part 1 of 2 5-18-23, 11. Xcel Revised Application Appendices Part 2 of 2 5-18-23, 12. PUC Order 8-10-23, 13. Xcel Application Route Permit Filing Letter 10-30-23, 14. Xcel Application Route Permit Application Text 10-30-23, 15. Xcel Application Route Permit App A and B 10-30-23, 16. MNEC RPA APPENDIX C - PART 1 OF 36 10-30-23, 17. MNEC RPA APPENDIX C - PART 2 OF 36 10-30-23, 18. MNEC RPA APPENDIX C - PART 3 OF 36 10-30-23, 19. -MNEC RPA APPENDIX C - PART 4 OF 36 10-30-23, 20. MNEC RPA APPENDIX C - PART 5 OF 36 10-30-23, 21. -MNEC RPA APPENDIX C - PART 6 OF 36 10-30-23, 22. MNEC RPA APPENDIX C - PART 7 OF 36 10-30-23, 23. MNEC RPA APPENDIX C - PART 8 OF 36 10-30-23, 24. MNEC RPA APPENDIX C - PART 9 OF 36 10-30-23, 25. MNEC RPA APPENDIX C - PART 10 OF 36 10-30-23, 26. MNEC RPA APPENDIX C - PART 11 OF 36 10-30-23, 27. MNEC RPA APPENDIX C - PART 12 OF 36 10-30-23, 28. MNEC RPA APPENDIX C - PART 13 OF 36 10-30-23, 29. MNEC RPA APPENDIX C - PART 14 OF 36 10-30-23, 30. MNEC RPA APPENDIX C - PART 15 OF 36 10-30-23, 31. MNEC RPA APPENDIX C - PART 16 OF 36 10-30-23, 32. MNEC RPA APPENDIX C - PART 17 OF 36 10-30-23, 33. MNEC RPA APPENDIX C - PART 18 OF 36 10-30-23, 34. MNEC RPA APPENDIX C - PART 19 OF 36 10-30-23, 35. MNEC RPA APPENDIX C - PART 20 OF 36 10-30-23, 36. MNEC RPA APPENDIX C - PART 21 OF 36 10-30-23, 37. MNEC RPA APPENDIX C - PART 22 OF 36 10-30-23, 38. MNEC RPA APPENDIX C - PART 23 OF 36 10-30-23, 39. MNEC RPA APPENDIX C - PART 24 OF 36 10-30-23, 40. MNEC RPA APPENDIX C - PART 25 OF 36 10-30-23, 41. MNEC RPA APPENDIX C - PART 26 OF 36 10-30-23, 42. MNEC RPA APPENDIX C - PART 27 OF 36 10-30-23, 43. MNEC RPA APPENDIX C - PART 28 OF 36 10-30-23, 44. MNEC RPA APPENDIX C - PART 29 OF 36 10-30-23, 45. MNEC RPA APPENDIX C - PART 30 OF 36 10-30-23, 46. MNEC RPA APPENDIX C - PART 31 OF 36 10-30-23, 47. MNEC RPA APPENDIX C - PART 32 OF 36 10-30-23, 48. MNEC RPA APPENDIX C - PART 33 OF 36 10-30-23, 49. MNEC RPA APPENDIX C - PART 34 OF 36 10-30-23, 50. MNEC RPA APPENDIX C - PART 35 OF 36 10-30-23, 51. MNEC RPA APPENDIX C - PART 36 OF 36 10-30-23, 52. Xcel Application Route Permit Appendix D-E 10-30-23, 53. Xcel Application Route Permit Appendix F-H 10-30-23, 54. Xcel PUBLIC Application Route Permit Appendix I-K 10-30-23, 55. Xcel Application Route Permit Appendix L 10-30-23, 56. PUC Order 1-16-24, 57. PUC Notice and Order for Hearing 1-24-24, 58. Xcel Response 3-18-24, 59. 1 DOC EERA Comments 4-17-24, 60. 2 DOC EERA Comments 4-17-24, 61. 3 DOC EERA Comments 4-17-24, 62. Xcel Response 4-23-24, 63. Briefing Paper
|
title
** E002/CN-22-131; Northern States Power Co. d/b/a Xcel
E002/TL-22-132 Energy
In the Matter of the Application of Northern States Power Co. d/b/a Xcel Energy for a Certificate of Need and Route Permit for the Minnesota Energy Connection Project in Sherburne, Stearns, Kandiyohi, Wright, Meeker, Chippewa, Yellow Medicine, Renville, Redwood, and Lyon counties in Minnesota.
1. What action should the Commission take concerning route alternatives to be evaluated in the environmental impact statement?
2. What actions, if any, should the Commission take concerning other procedural items? (PUC: Ek)
|