** E002/M-17-797 Northern States Power Company, d/b/a Xcel Energy
In the Matter of the Petition of Northern States Power Company for Approval of the Transmission Cost Recovery Rider Revenue Requirements for 2017 and 2018, and Revised Adjustment Factors.
1. Should the Commission approve or modify Xcel Energy’s proposed rate of return used for determining the Transmission Cost Recovery Rider revenue requirements?
2. Should the Commission approve or modify Xcel Energy’s proposed proration for Accumulated Deferred Income Taxes?
3. Should the Commission approve or modify Xcel Energy’s request for cost recovery of the ADMS Distribution-Grid Modernization project?
4. Should the Commission approve or modify Xcel Energy’s 2017 and 2018 revenue requirements for the projects eligible for cost recovery through the Transmission Cost Recovery Rider?
5. Should the Commission approve or modify Xcel Energy’s request to modify its Transmission Cost Recovery Tariff, 2016 True-up and Tracker Balance report, adjustment factors, and customer notice? (PUC: Bonnett, Alonso, Debleeckere)