File #: Details 2019-136    Version: Name:
Type: TL - Transmission Line Status: Agenda Ready
File created: 8/12/2019 In control: PUC Agenda Meeting
On agenda: 10/22/2020 Final action:
Title: * E229/TL-18-755 Detroit Lakes Public Utilities In the Matter of the Application of Detroit Lakes Public Utilities for a High-Voltage Transmission Line Route Permit in Becker County. 1. Should the Commission find that the environmental assessment and the record created at the public hearing adequately address the issues identified in the scoping decision? 2. Should the Commission issue a route permit identifying a specific route and permit conditions for the Detroit Lakes Public Utility 115 kV High Voltage Transmission Line Project in Lake View Township, Becker County? (PUC: Kaluzniak)
Attachments: 1. 1 DLPU - Application - 7-9-2019, 2. 2 DLPU - Application - 7-9-2019, 3. 3 DLPU - Application - 7-9-2019, 4. 4 DLPU - Application - 7-9-2019, 5. 5 DLPU - Application - 7-9-2019, 6. 6 DLPU - Application - 7-9-2019, 7. 7 DLPU - Application - 7-9-2019, 8. PUC - Order - 10-28-2019, 9. 1 DLPU - Rev Application - 11-6-2019, 10. 2 DLPU - Rev Application - 11-6-2019, 11. 3 DLPU - Rev Application - 11-6-2019, 12. 4 DLPU - Rev Application - 11-6-2019, 13. 5 DLPU - Rev Application - 11-6-2019, 14. 6 DLPU - Rev Application - 11-6-2019, 15. 7 DLPU - Rev Application - 11-6-2019, 16. 8 DLPU - Rev Application - 11-6-2019, 17. DOC - Scoping Decision - 2-27-2020, 18. 1 DOC - Assessment - 6-1-2020, 19. 2 DOC - Assessment - 6-1-2020, 20. 3 DOC - Assessment - 6-1-2020, 21. 4 DOC - Assessment - 6-1-2020, 22. 5 DOC - Assessment - 6-1-2020, 23. PUC - Notice - 6-10-2020, 24. DOC - Hearing Exhibit List - 7-14-2020, 25. DOC - Findings of Fact - 8-13-2020, 26. OAH - Summary - 9-1-2020, 27. Briefing Papers

title

*                     E229/TL-18-755                     Detroit Lakes Public Utilities

In the Matter of the Application of Detroit Lakes Public Utilities for a High-Voltage Transmission Line Route Permit in Becker County.

 

1.                     Should the Commission find that the environmental assessment and the record created at the public hearing adequately address the issues identified in the scoping decision?

2.                     Should the Commission issue a route permit identifying a specific route and permit conditions for the Detroit Lakes Public Utility 115 kV High Voltage Transmission Line Project in Lake View Township, Becker County? (PUC: Kaluzniak)