Title: ** G008/M-21-138 CenterPoint Energy Resources Corp., d/b/a CenterPoint Energy Minnesota Gas In the Matter of the Petition of CenterPoint Energy for Approval of a Recovery Process for Cost Impacts Due to February Extreme Gas Market Conditions. Should the Commission reconsider its October 19, 2022 Order Disallowing Recovery of Certain Natural Gas Costs and Requiring Further Action? If so, which disallowances should be changed and by how much? (PUC: Alonso) The Commission has the authority to accept or decline a petition for reconsideration with or without a hearing or oral argument (Minnesota Rules 7829.3000, Subpart 6) In other words, a decision on a petition for reconsideration can be made without taking oral comments at the Commission meeting.
Attachments: 1. PUC Order 10-19-22, 2. CenterPoint Petition 11-8-22, 3. OAG Answer 11-18-22, 4. DOC Answer 11-18-22, 5. CUB Answer 11-18-22, 6. City of Mpls Letter 11-18-22, 7. Briefing Papers

title

**                     G008/M-21-138                     CenterPoint Energy Resources Corp., d/b/a

                                                               CenterPoint Energy Minnesota Gas

In the Matter of the Petition of CenterPoint Energy for Approval of a Recovery Process for Cost Impacts Due to February Extreme Gas Market Conditions.

 

Should the Commission reconsider its October 19, 2022 Order Disallowing Recovery of Certain Natural Gas Costs and Requiring Further Action?

If so, which disallowances should be changed and by how much? (PUC: Alonso)

 

The Commission has the authority to accept or decline a petition for reconsideration with or without a hearing or oral argument (Minnesota Rules 7829.3000, Subpart 6) In other words, a decision on a petition for reconsideration can be made without taking oral comments at the Commission meeting.