Details 2021-265
| 1 | 1. | | C - Complaint | ** P421/C-20-432 Qwest Corporation d/b/a CenturyLink QC
In the Matter of Formal Complaint Regarding the Services Provided by the Qwest Corporation, d/b/a CenturyLink in Minnesota, on Behalf of the Communications Workers of America.
How should the Commission Proceed in this Matter? (PUC: Fournier) | |
Action details
|
Details 2021-270
| 1 | 2. | | TL - Transmission Line | ET2/TL-20-423 Great River Energy;
Otter Tail Power Company
In the Matter of the Application of Great River Energy and Otter Tail Power Company for a Route Permit for the Frazee to Erie 115 kV Transmission Line Project in Becker and Otter Tail Counties. (PUC: Bruce; DOC: Levi) | |
Action details
|
Details 2021-259
| 1 | 3. | | CN - Certificate of Need | ** IP7041/GS-20-763; Byron Solar, LLC
IP7041/CN-20-764;
IP7041/TL-20-765
In the Matter of the Application of Byron Solar, LLC for a Certificate of Need, Site Permit, and Route Permit for the up to 200 MW Byron Solar Project and 345 kV Transmission Line in Dodge and Olmsted Counties, Minnesota.
1. Should the Commission adopt the administrative law judge's findings of fact, conclusions of law, and recommendation?
2. Should the Commission find that the environmental assessment and the record on this Project adequately address the issues identified in the Scoping Decision?
3. Should the Commission grant a certificate of need for the Byron Solar Project proposed in Dodge and Olmsted Counties, Minnesota?
4. Should the Commission grant a site permit for the up to 200 MW Byron Solar Project in Dodge County, Minnesota?
5. Should the Commission issue a route permit for the 345 kV high voltage transmission line for the proposed solar photovoltaic electric generating facility? (PUC: Kaluzniak) | |
Action details
|