Title:
|
** E015/PA-17-400 Minnesota Power
In the Matter of the Petition of Minnesota Power for Approval of the Purchase of Transmission Assets and Approval of a Substation Access Easement Agreement with United Taconite, LLC.
1. Should the Commission approve the Transmission Asset and Substation Access Agreement between United Taconite, LLC and Minnesota Power?
2. Should the Commission accept MP's explanation of the actual revenue requirement impact on the rate case of the purchase of the United Taconite Transmission Assets and MP's explanation of why this is reasonable? (PUC: Bartusch, Alonso)
|