Title:
|
** PL9/CN-07-465 Enbridge Energy (Southern Lights) LLC
In the Matter of the Application of Enbridge Energy, Limited Partnership and Enbridge Pipelines (Southern Lights) LLC for a Certificate of Need for the Alberta Clipper Pipeline Project and Southern Lights Project.
1. Should the Commission grant a request to reconsider its May 6, 2026, Order concerning the need for recertification?
2. Should the Commission grant a request to reconsider its May 6, 2026, Order requiring preparation of an environmental assessment worksheet? (PUC: Janezich, Eknes)
The Commission has the authority to accept or decline a petition for reconsideration with or without a hearing or oral argument (Minnesota Rules 7829.3000, Subpart 6). In other words, a decision on a petition for reconsideration can be made without taking oral comments at the Commission meeting.
|