** IP7103/GS-22-451 Enbridge Solar (Plummer), LLC
In the Matter of the Application of Enbridge Solar (Plummer), LLC for a Site Permit for the up to 130 MW Plummer Solar Project in Red Lake County, MN.
1. Should the Commission adopt the Administrative Law Judge's Findings of Fact, Conclusions of Law, and Recommendation?
2. Should the Commission find that the environmental assessment and the record created at the public hearing adequately address the issues identified in the scoping decision?
3. Should the Commission issue a site permit for the up to 130-megawatt Plummer Solar Energy Generating System? (PUC: Lobby, Janezich)
|
Attachments:
|
1. Enbridge Application pt 1 4-2-24, 2. Enbridge Application pt 2 4-2-24, 3. Enbridge Application pt 3 4-2-24, 4. Enbridge Application pt 4 4-2-24, 5. Enbridge Application pt 5 4-2-24, 6. Enbridge Application pt 6 4-2-24, 7. Enbridge Application pt 7 4-2-24, 8. Enbridge Application pt 8 4-2-24, 9. Enbridge PUBLIC Application pt 9 4-2-24, 10. Enbridge Application pt 10 4-2-24, 11. Enbridge Application pt 11 4-2-24, 12. Enbridge Application pt 12 4-2-24, 13. Enbridge Application pt 13 4-2-24, 14. Enbridge PUBLIC Application pt 15 4-2-24, 15. Enbridge Application pt 16 4-2-24, 16. Enbridge Application pt 17 4-2-24, 17. Enbridge Application pt 18 4-2-24, 18. PUC Notice of Comment Period–Application Completeness 4-4-24, 19. EERA C & R on Application Completeness 4-18-24, 20. Enbridge Reply Comments 4-25-24, 21. PUC Order–Application Completeness 5-7-24, 22. PUC Notice of Public Info 5-14-24, 23. IUOE Local 49 Comments 6-12-24, 24. Enbridge Scoping Comments 6-13-24, 25. Liuna Comments 6-14-24, 26. EERA Written Comments on EA Scope 6-26-24, 27. EERA Oral Comments on EA Scope 6-26-24, 28. OAH First Prehearing Order 6-28-24, 29. EERA EA Scoping Decision 7-8-24, 30. EERA Notice of EA Scoping Decision 7-11-24, 31. PUC Sample Solar Site Permit 8-14-24, 32. Enbridge PUBLIC SHPO Correspondence Letter 8-15-24, 33. OAH Second Prehearing Order 10-18-24, 34. EERA–Plummer Solar EA pt 1 10-28-24, 35. EERA–Plummer Solar EA pt 2 10-28-24, 36. EERA–Plummer Solar EA pt 3 10-28-24, 37. EERA–Plummer Solar EA pt 4 10-28-24, 38. EERA–Plummer Solar EA pt 5 10-28-24, 39. PUC Notice of Public Hearings 10-28-24, 40. EERA Notification of EA to Agencies and THPO’s pt 1 10-30-24, 41. EERA Notification of EA to Agencies and THPO’s pt 2 10-30-24, 42. PUC Public Comment–MPCA 11-20-24, 43. PUC Public Comment–Upper Sioux THPO 12-3-24, 44. DNR Comments 12-6-24, 45. IUOE Local 49 and NCSRC Comments 12-6-24, 46. EERA Hearing Comments 12-6-24, 47. Enbridge Reply Comments 12-9-24, 48. Enbridge Proposed Findings pt 1 12-17-24, 49. Enbridge Proposed Findings pt 2 12-17-24, 50. EERA Edits to Proposed Findings 1-8-25, 51. EERA Response 1-8-25, 52. ALJ Report 2-4-25, 53. Plummer Solar Exceptions to ALJ Report 2-14-25, 54. EERA Exceptions to ALJ Report 2-18-25, 55. Briefing Papers, 56. Staff Decision Option 6A
|
title
** IP7103/GS-22-451 Enbridge Solar (Plummer), LLC
In the Matter of the Application of Enbridge Solar (Plummer), LLC for a Site Permit for the up to 130 MW Plummer Solar Project in Red Lake County, MN.
1. Should the Commission adopt the Administrative Law Judge’s Findings of Fact, Conclusions of Law, and Recommendation?
2. Should the Commission find that the environmental assessment and the record created at the public hearing adequately address the issues identified in the scoping decision?
3. Should the Commission issue a site permit for the up to 130-megawatt Plummer Solar Energy Generating System? (PUC: Lobby, Janezich)
|