Title: ** ET2/TL-24-132 Great River Energy In the Matter of the Application of Great River Energy for a Route Permit Application for the Laketown 115-kV Transmission Line in Carver County, Minnesota. 1. Should the Commission adopt the administrative law judge's findings of fact, conclusions of law, and recommendation? 2. Should the Commission determine that the environmental assessment is adequate? 3. Should the Commission grant a route permit for the proposed transmission line project? (PUC: Lobby, Hicks)
Attachments: 1. GRE 1 Initial Filing 8-19-24, 2. GRE 2 Initial Filing 8-19-24, 3. GRE 3 Initial Filing 8-19-24, 4. GRE 4 Initial Filing 8-19-24, 5. GRE 5 Initial Filing 8-19-24, 6. GRE 6 Initial Filing 8-19-24, 7. GRE 7 Initial Filing 8-19-24, 8. GRE 8 Initial Filing 8-19-24, 9. GRE 9 Initial Filing 8-19-24, 10. GRE 10 Initial Filing 8-19-24, 11. GRE 11 Initial Filing 8-19-24, 12. GRE 12 Initial Filing 8-19-24, 13. GRE 13 Initial Filing 8-19-24, 14. GRE 18 Initial Filing 8-19-24, 15. GRE 19 Initial Filing 8-19-24, 16. GRE 20 Initial Filing 8-19-24, 17. GRE 21 Initial Filing 8-19-24, 18. PUC Order 10-1-24, 19. DOC EERA Comments 12-12-24, 20. PUC Order 2-4-25, 21. GRE 1 Direct Testimony 4-22-25, 22. GRE 2 Direct Testimony 4-22-25, 23. GRE 3 Direct Testimony 4-22-25, 24. DOC EERA Environmental Assessment 4-8-25, 25. PUC Notice 5-1-25, 26. GRE 1 Comments 5-13-25, 27. GRE 2 Comments 5-13-25, 28. DNR 1 Comments 6-2-25, 29. DNR 2 Comments 6-2-25, 30. IVMWG Comments 6-2-25, 31. DOC EERA Comments 6-2-25, 32. GRE Comments 6-9-25, 33. GRE 1 Proposed FOF 6-9-25, 34. GRE 2 Proposed FOF 6-9-25, 35. OAH Report 7-17-25, 36. GRE Exceptions to ALJ 7-30-25, 37. PUC EIP Exceptions 7-31-25, 38. Briefing Papers, 39. 24-132 Tuma Modified and New DOs
Date Ver.Action ByActionAction DetailsMeeting Details
No records to display.

title

**                     ET2/TL-24-132                      Great River Energy

In the Matter of the Application of Great River Energy for a Route Permit Application for the Laketown 115-kV Transmission Line in Carver County, Minnesota. 

 

1.                     Should the Commission adopt the administrative law judge’s findings of fact, conclusions of law, and recommendation?

2.                     Should the Commission determine that the environmental assessment is adequate?

3.                     Should the Commission grant a route permit for the proposed transmission line project?  (PUC: Lobby, Hicks)