File #: Details 2025-002    Version: Name:
Type: TL - Transmission Line Status: Agenda Ready
File created: 1/8/2025 In control: PUC Agenda Meeting
On agenda: 5/22/2025 Final action:
Title: * IP7138/ESS-24-294; Spearmint Energy (Midwater BESS, LLC) IP7138/TL-24-295 In the Matter of the Application of Midwater BESS, LLC for a site permit for the up to 150 MW Midwater Energy Storage project in Freeborn County, Minnesota. In the Matter of the Application of Midwater BESS, LLC for a route permit for the 161kV transmission line for the Midwater Energy Storage project in Freeborn County, Minnesota. 1. What action should the Commission take concerning site and route alternatives to be evaluated in the environmental assessment? 2. What actions, if any, should the Commission take concerning other procedural items? (PUC: Harvieux)
Attachments: 1. 1 Application 11-19-24, 2. 2 Application 11-19-24, 3. 3 Application 11-19-24, 4. 4 Application 11-19-24, 5. 5 Application 11-19-24, 6. 6 Application 11-19-24, 7. 7 Application 11-19-24, 8. 8 Application 11-19-24, 9. 9 Application 11-19-24, 10. 10 Application 11-19-24, 11. 11 Application 11-19-24, 12. 12 Application 11-19-24, 13. 13 Application 11-19-24, 14. DOC EERA Comments 4-9-25, 15. PUC Public Comment Butler County Board of Supervisors 4-15-25, 16. DOC EERA Comments Freeborn County Resolution 4-17-25, 17. Midwater BESS Comments 4-21-25, 18. PUC Public Comment Butler County Board of Supervisors 4-22-25, 19. DOC EERA Comments Shell Rock River Watershed District 4-24-25, 20. IUOE Local 49 & NCSRC of Carpenters Comments 4-21-25, 21. Public Comments Batch No. 3 4-25-25, 22. Public Comments Batch No. 4 4-30-25, 23. DOC EERA Comment Letter on EA Scope 5-5-25, 24. Public Comments Batch No. 5 5-5-25, 25. Briefing Papers
Date Ver.Action ByActionAction DetailsMeeting Details
No records to display.

title

*                     IP7138/ESS-24-294;                     Spearmint Energy (Midwater BESS, LLC)

                     IP7138/TL-24-295

In the Matter of the Application of Midwater BESS, LLC for a site permit for the up to 150 MW Midwater Energy Storage project in Freeborn County, Minnesota.

In the Matter of the Application of Midwater BESS, LLC for a route permit for the 161kV transmission line for the Midwater Energy Storage project in Freeborn County, Minnesota.

 

1.                     What action should the Commission take concerning site and route alternatives to be evaluated in the environmental assessment?

2.                     What actions, if any, should the Commission take concerning other procedural items? (PUC: Harvieux)