Title: * IP7013/WS-19-619 Apex Clean Energy Holdings, LLC d/b/a Big Bend Wind, LLC In the Matter of the Application of Big Bend Wind, LLC for a Large Wind Energy Conversion System Site Permit for the up to 300 MW Big Bend Wind Project in Cottonwood and Watonwan Counties, Minnesota. Should the Commission reconsider the decision to approve the site permit amendment for the Big Bend Wind Project? (PUC: Davis) The Commission has the authority to accept or decline a petition for reconsideration with or without a hearing or oral argument (Minnesota Rules 7829.3000, Subpart 6). In other words, a decision on a petition for reconsideration can be made without taking oral comments at the Commission meeting.
Attachments: 1. PUC Order 2-25-26, 2. Hutchison Petition for Reconsideration 3-3-26, 3. BBW Answer to Petition 3-13-26
Date Ver.Action ByActionAction DetailsMeeting Details
No records to display.

title

*                     IP7013/WS-19-619                     Apex Clean Energy Holdings, LLC d/b/a

                                                               Big Bend Wind, LLC

In the Matter of the Application of Big Bend Wind, LLC for a Large Wind Energy Conversion System Site Permit for the up to 300 MW Big Bend Wind Project in Cottonwood and Watonwan Counties, Minnesota.

 

Should the Commission reconsider the decision to approve the site permit amendment for the Big Bend Wind Project? (PUC: Davis)

 

The Commission has the authority to accept or decline a petition for reconsideration with or without a hearing or oral argument (Minnesota Rules 7829.3000, Subpart 6). In other words, a decision on a petition for reconsideration can be made without taking oral comments at the Commission meeting.