** IP6557/WS-06-91 Northern States Power d/b/a Xcel Energy
In the Matter of the Site Permit Amendment to Repower the 98.9 Megawatt Mower County Wind Energy Center Project and Associated Facilities in Mower County, Minnesota.
1. What, if any, action should the Commission take regarding the complaint from the City of Grand Meadow as first reported in Xcel Energy's Monthly Complaint Report filed on February 15, 2024?
2. What authority does the Commission have to order removal of the wind turbine blades from the city industrial park?
3. What contractual remedies does Xcel Energy have with NextEra Energy Resources or others regarding proper disposal and recycling of the turbine blades? (PUC: Panait)
|