title
* E002/TL-12-1151 Northern States Power Company d/b/a
Xcel Energy
In the Matter of the Application of Xcel Energy for a Route Permit for the Kohlman Lake to Goose Lake 115 kV Transmission Line Upgrade Project in Ramsey County, Minnesota.
Should the Commission find that the environmental assessment and the record created at the public hearing adequately address the issues identified in the scoping decision? Should the Commission issue a route permit identifying a specific route and permit conditions for the Kohlman Lake to Goose Lake 115 kV Transmission Line Project in Ramsey County? (PUC: Ek)