Title: ** E002/M-23-524 Northern States Power Co. d/b/a Xcel Energy In the Matter of the Petition of Xcel Energy for Approval of a Residential Time of Use Rate Design. Should the Commission approve Xcel Energy's petition for a residential time-of-use rate design as found in its August 16, 2024 letter? (PUC: Dornfeld)
Attachments: 1. Xcel Revised Petition 8-16-24, 2. Public Comment, S. Adams 8-30-24, 3. Public Comment, M. Kreuzer 8-30-24, 4. Public Comment, A. Adams 9-30-24, 5. MNSEIA Comments? 10-15-25, 6. Fresh Energy Comments 10-15-24, 7. OAG Comments 10-15-24, 8. GridX, Inc. Comments? 10-15-24, 9. CUB Comments 10-15-24, 10. DOC Comments 10-15-24, 11. Uplight Comments 10-15-24, 12. CEE Comments 1-15-24, 13. ILSR Reply Comments? 11-13-24, 14. Fresh Energy Reply Comments 11-14-24, 15. OAG Reply Comments 11-14-24, 16. MNSEIA Reply Comments? 11-14-24, 17. Xcel Energy Reply Comments 11-14-24, 18. Clear Energy Coalition Reply Comments? 11-14-24, 19. Public Comment, J. Holm 11-14-24, 20. CUB Reply Comments 11-14-24, 21. DOC Reply Comments 11-14-24, 22. Public Comment, J. Jacoby 11-21-24, 23. Xcel Energy Initial Petition 12-22-23, 24. Xcel Revised Petition Att B 8-16-24, 25. 17-776 PUC Order 8-1-7-18, 26. 17-775 Xcel Energy Residential Time of Use Rate Design Pilot Program 11-1-17, 27. Briefing Papers, 28. Revised Decision Options, 29. Decision Options-Commissioner Sullivan
Date Ver.Action ByActionAction DetailsMeeting Details
No records to display.

title

**                     E002/M-23-524                     Northern States Power Co. d/b/a Xcel Energy

In the Matter of the Petition of Xcel Energy for Approval of a Residential Time of Use Rate Design.

 

Should the Commission approve Xcel Energy’s petition for a residential time-of-use rate design as found in its August 16, 2024 letter? (PUC: Dornfeld)