Title: ** E017/M-24-204 Otter Tail Power Co. In the Matter of Otter Tail Power Company's Petition for Approval of the Annual Rate Update to its Transmission Cost Recovery Rider Annual Adjustment. 1. Should the Commission approve Otter Tail Power Company's 9th annual rate update to its Transmission Cost Recovery Rider (TCRR)? 2. Should the Commission determine Otter Tail's Milbank Area Reliability project is eligible for recovery through the TCRR under Minn. Stat. ? 216B.16, subd. 7b? (PUC: Ubani)
Attachments: 1. PUC BP 5-6-25, 2. OTP PUBLIC Filing 7-3-25, 3. DOC Letter 7-29-25, 4. OTP Response 8-13-25, 5. Briefing Papers
Date Ver.Action ByActionAction DetailsMeeting Details
No records to display.

title

**                     E017/M-24-204                     Otter Tail Power Co.

In the Matter of Otter Tail Power Company's Petition for Approval of the Annual Rate Update to its Transmission Cost Recovery Rider Annual Adjustment.

 

1.                     Should the Commission approve Otter Tail Power Company’s 9th annual rate update to its Transmission Cost Recovery Rider (TCRR)?

2.                     Should the Commission determine Otter Tail’s Milbank Area Reliability project is eligible for recovery through the TCRR under Minn. Stat. § 216B.16, subd. 7b? (PUC: Ubani)