Title:
|
* E015,ET2,E017/CN- Minnesota Power;
25-109; Great River Energy;
Otter Tail Power Co.
In the Matter of Application of Minnesota Power, Great River Energy, and Otter Tail Power Company for a Certificate of Need for the Maple River to Cuyuna 345kV Transmission Line Project.
1. Should the Commission accept the certificate of need application as substantially complete?
2. Should the Commission authorize review of the certificate of need application using the informal process or refer the matter to the Court of Administrative Hearings for contested case proceedings?
3. Should the Commission consider any additional procedural items? (PUC: Harvieux)
|