Title: *** E022/M-25-289 Northern States Power Co. d/b/a Xcel Energy In the Matter of Xcel Energy's Petition for Approval of Large General Time of Day Service Customer and Large Peak Controlled Time of day Service Tariffs. 1. Should the Commission approve, reject, or modify Xcel Energy's proposed Large General and Large Peak Controlled Time of Day Service tariffs, associated rider revisions, and the Retail Customer Form Electric Service Agreement (ESA)? 2. Should the Commission approve, reject, or modify the Incremental Cost Test (ICT)? 3. Should the Commission limit the use of the ICT to an interim basis and instead address cost allocations for these new sub-classes through a traditional Class Cost of Service Study in a future general rate case? 4. Should the Commission set the demand size threshold for the new tariffs at 100 MW, or adopt an alternative threshold? 5. Should the Commission include additional criteria when determining tariff applicability? 6. Should the Commission modify the ...
Attachments: 1. XE Petition 7-16-25, 2. XE PUBLIC Reply Comments 11-5-25, 3. XE Supplemental Comments 12-5-25, 4. XE Proposed Decision Options 3-27-26, 5. DOC Comments 10-13-25, 6. DOC Supplemental Comments 12-5-25, 7. OAG, DOC, CUB, MCEA, ELPC, VS, FE Letter 3-6-26, 8. DOC Proposed Decision Options 3-27-26, 9. OAG Extension Request 9-19-25, 10. OAG Comments 10-13-25, 11. OAG Reply Comments 11-5-25, 12. OAG Proposed Decision Options 3-25-26, 13. CUB Comments 10-13-25, 14. CUB Request 10-15-25, 15. CUB Supplemental Comments 12-5-25, 16. CUB Proposed Decision Options 3-27-26, 17. CGA Comments 10-13-25, 18. CGA Supplemental Comments 12-5-25, 19. CGA Preferred Decision Options 3-27-26, 20. Cloud HQ Comments 10-13-25, 21. Cloud HQ Reply Comments 11-5-25, 22. Cloud HQ Supplemental Comments 12-5-25, 23. Cloud HQ Decision Options 3-27-26, 24. DCC Comments 10-13-25, 25. DCC Reply Comments 11-5-25, 26. DCC Supplemental Comments 12-5-25, 27. DCC Proposed Decision Options 3-27-26, 28. ELPC & VS Comments 10-13-25, 29. ELPC & VS Supplemental Comments 12-5-25, 30. ELPC & VS Proposed Decision Options 3-27-26, 31. FE & MCEA Comments 10-13-25, 32. FE & MCEA Proposed Decision Options 3-27-26, 33. GP Comments 10-13-25, 34. GP Supplemental Comments 12-5-25, 35. GE Proposed Decision Options 3-27-26, 36. Google Comments 10-13-25, 37. Google Reply Comments 11-5-25, 38. Google Supplemental Comments 12-5-25, 39. Google Proposed Decision Options 3-27-26, 40. Legaletric-NoCapX Request 10-17-25, 41. LiUNA Comments 10-14-25, 42. LiUNA Supplemental Comments 12-8-25, 43. LiUNA Proposed Decision Options 3-27-26, 44. TCM Comments 10-13-25, 45. TCM Supplemental Comments 12-5-25, 46. TCM Proposed Decision Options 3-30-26, 47. XLI Comments 12-5-25, 48. XLI Proposed Decision Options 3-27-26, 49. Public Comment Swindle 9-24-25, 50. Public Comment Wickstrom 9-30-25, 51. Briefing Papers, 52. New and Modified Decision Options - Commissioner Ham, 53. Deliberation Outline, 54. CUB New Decision Options, 55. OAG New Decision Options, 56. Xcel New Decision Options, 57. Google New Modified Decision Options
Date Ver.Action ByActionAction DetailsMeeting Details
No records to display.
title
*** E022/M-25-289 Northern States Power Co. d/b/a Xcel Energy
In the Matter of Xcel Energy's Petition for Approval of Large General Time of Day Service Customer and Large Peak Controlled Time of day Service Tariffs.

1. Should the Commission approve, reject, or modify Xcel Energy's proposed Large General and Large Peak Controlled Time of Day Service tariffs, associated rider revisions, and the Retail Customer Form Electric Service Agreement (ESA)?
2. Should the Commission approve, reject, or modify the Incremental Cost Test (ICT)?
3. Should the Commission limit the use of the ICT to an interim basis and instead address cost allocations for these new sub-classes through a traditional Class Cost of Service Study in a future general rate case?
4. Should the Commission set the demand size threshold for the new tariffs at 100 MW, or adopt an alternative threshold?
5. Should the Commission include additional criteria when determining tariff applicability?
6. Should the Commission modify the minimum ESA term length?
7. Should the Commission allow Xcel to remove the Plant Stratification process and shift more cost recovery to demand charges and less to energy charges?
8. Should the Commission modify the minimum billing demand and exit fee calculations?
9. Should the Commission treat super-large customers as a separate customer class rather than an incremental sub-class, and direct Xcel to allocate shared versus dedicated system resources accordingly?
10. Should the Commission determine that the Petition complies with the Commission's IRP Order and Minn. Stat. ? 216B.1622?
11. Should the Commission explicitly require Xcel to provide "bring your own generation" (BYOG) avenues and develop a voluntary clean energy and capacity tariff by a specific date?
12. Should the Commission direct Xcel to implement an expedited interconnection process for clean or flexible large loads?
13. Should the Commission require Xcel to submit recurring reports detailing the number of new la...

Click here for full text