Skip to main content
File #: Details 2024-162    Version: Name:
Type: TL - Transmission Line Status: Agenda Ready
File created: 10/2/2024 In control: PUC Agenda Meeting
On agenda: 9/11/2025 Final action:
Title: ** ET3/TL-24-95 Dairyland Power Cooperative In the Matter of the Application of Dairyland Power Cooperative for a Route Permit for a 161 kV Transmission Line in Fillmore County, Minnesota. 1. Should the Commission adopt the Administrative Law Judge's Findings of Fact, Conclusions of Law, and Recommendations? 2. Should the Commission find that the Environmental Assessment and record created at the public hearing adequately address the issues identified in the scoping decision? 3. Should the Commission grant a route permit for Dairyland's 161 kV Transmission Line in Fillmore County? (PUC: Janezich)
Attachments: 1. DPC Route Permit App 8-26-24, 2. DPC Route Permit App App A 8-26-24, 3. DPC Route Permit App App B 8-26-24, 4. DPC Route Permit App App C 8-26-24, 5. DPC Route Permit App App D 8-26-24, 6. DPC Route Permit App App E 8-26-24, 7. DPC Route Permit App App F 8-26-24, 8. DPC Route Permit App App G 8-26-24, 9. DPC Route Permit App App H 8-26-24, 10. DPC Route Permit App App I 8-26-24, 11. DPC Route Permit App App J 8-26-24, 12. DPC Project Notice 8-26-24, 13. DPC Notice of Intent 8-26-24, 14. PUC Order 10-15-24, 15. PUC Notice 10-22-24, 16. MN DNR Comments 12-3-24, 17. MN DNR Comments Att 12-3-24, 18. OAH Order 12-4-24, 19. DPC Reply Comments 12-13-24, 20. Information Scoping Meeting Transcripts 12-17-24, 21. DOC EERA Scoping Summary and Recommendation 12-19-24, 22. PUC Order 1-7-25, 23. DOC EERA Scoping Decision 1-23-25, 24. OAH Second Prehearing Order 2-18-25, 25. PUC Notice of Public Hearings and Availability of EA 4-7-25, 26. DPC Yvonne Gildemaster Testimony 4-8-25, 27. DOC EERA Environmental Assessment 4-11-25, 28. DPC Comments on EA and DRP 4-17-25, 29. PUC Public Comments Corey Prins 5-2-25, 30. MN DNR Comments 5-13-25, 31. MN DNR Comments Att 5-13-25, 32. VMPWG Comments 5-14-25, 33. PUC 1 Public Comment 5-19-25, 34. PUC 2 Public Comment 5-19-25, 35. DPC Proposed Findings of Fact, Conclusions of Law, and Recommendations 5-27-25, 36. DPC Response to Comments 5-27-25, 37. OAH Findings of Fact, Conclusions of Law and Recommendations 7-28-25, 38. PUC-EIP Exceptions to ALJ Report 8-11-25, 39. DPC Exceptions to ALJ Report 8-12-25, 40. Briefing Papers
Date Ver.Action ByActionAction DetailsMeeting Details
No records to display.

title

**                     ET3/TL-24-95                     Dairyland Power Cooperative

In the Matter of the Application of Dairyland Power Cooperative for a Route Permit for a 161 kV Transmission Line in Fillmore County, Minnesota.

 

1.                     Should the Commission adopt the Administrative Law Judge’s Findings of Fact, Conclusions of Law, and Recommendations?

2.                     Should the Commission find that the Environmental Assessment and record created at the public hearing adequately address the issues identified in the scoping decision?

3.                     Should the Commission grant a route permit for Dairyland’s 161 kV Transmission Line in Fillmore County? (PUC: Janezich)