** E999/CI-19-704 All Electric Utilities
In the Matter of an Investigation into Self-Commitment and Self-Scheduling of Large Baseload Generation Facilities.
1. Have the utilities provided adequate information in the 2026 compliance filings on self-commitment?
2. Should the utilities be required to provide additional information or take additional steps regarding self-commitment at this time?
3. Should the filing of this report be combined with the annual fuel-true up reporting, as recommended by Joint Parties in the December 29, 2025 letter?
4. Should the filing requirements for future years be modified? (PUC: Manning, Andringa)
|