Title: ** E015/CN-12-1163 Minnesota Power In the Matter of the Application of Minnesota Power for a Certificate of Need for the 500 kilovolt Great Northern High-Voltage Transmission Line Project from the Manitoba, Canada - Minnesota Border to the Blackberry Substation near Grand Rapids, Minnesota. Should the Commission adopt the Administrative Law Judge Report? Do the Environmental Report and record of the Public Hearing address the items identified in the scoping decision? Should the Commission grant a Certificate of Need for the proposed project? If approved, should the Commission include any additional conditions? (PUC: Kaluzniak)
Attachments: 1. MP Initial Filing pt 1 of 24 10-21-13, 2. MP Initial Filing pt 2 of 24 10-21-13, 3. MP Initial Filing pt 3 of 24 10-21-13, 4. MP Initial Filing pt 4 of 24 10-21-13, 5. MP Initial Filing pt 5 of 24 10-21-13, 6. MP Initial Filing pt 7 of 24 10-21-13, 7. MP Initial Filing pt 8 of 24 10-21-13, 8. MP Initial Filing pt 9 of 24 10-21-13, 9. MP Initial Filing pt 10 of 24 10-21-13, 10. MP Initial Filing pt 11 of 24 10-21-13, 11. MP Initial Filing pt 12 of 24 10-21-13, 12. MP Initial Filing pt 13 of 24 10-21-13, 13. MP Initial Filing pt 14 of 24 10-21-13, 14. MP Initial Filing pt 15 of 24 10-21-13, 15. MP Initial Filing pt 16 of 24 10-21-13, 16. MP Initial Filing pt 17 of 24 10-21-13, 17. MP Initial Filing pt 18 of 24 10-21-13, 18. MP Initial Filing pt 19 of 24 10-21-13, 19. MP Initial Filing pt 20 of 24 10-21-13, 20. MP Initial Filing pt 21 of 24 10-21-13, 21. MP Initial Filing pt 22 of 24 10-21-13, 22. MP Initial Filing pt 23 of 24 10-21-13, 23. MP Initial Filing pt 24 of 24 10-21-13, 24. DER Comments 11-19-13, 25. Regional Utilities Comments 11-19-13, 26. Large Power Intervenors Comments 11-19-13, 27. DER Correction to Comments 11-21-13, 28. MP Reply Comments 12-3-13, 29. PUC Briefing Papers 12-12-13, 30. Order Accepting Application as Complete 1-8-14, 31. DOC EERA Environmental Report Scoping Decision 4-23-14, 32. MP Application Update 5-15-14, 33. DOC EERA Environmental Report 7-14-14, 34. MP Direct Testimony of David McMillan 8-8-14, 35. MP Direct Testimony of Scott Hoberg 8-8-14, 36. MP Direct Testimony of James Atkinson 8-8-14, 37. MP Direct Testimony of Christian Winter 8-8-14, 38. DOC DER Direct Testimony and Attachments of Rakow 9-19-14 TS, 39. DOC DER Direct Testimony and Attachments of Rakow 9-19-14 PUBLIC, 40. DOC DER Direct Testimony and Attachments of Shah 9-19-14, 41. MP Protective Agreement Exhibit A 10-15-14, 42. MP Rebuttal of David McMillan 10-24-14, 43. MP Rebuttal of Michael Donahue 10-24-14, 44. DOC DER Rebuttal Rakow 10-24-14, 45. LPI Protective Order all pts 10-24-14, 46. Public Hearing Comments and Exhibits - 7 pts 11-3-14, 47. MP Surrebuttal of David McMillan 11-7-14, 48. MP Surrebuttal of Allan Rudeck 11-7-14, 49. DOC DER Surrebuttal of Johnson 11-7-14, 50. DOC DER Surrebuttal of Rakow 11-7-14, 51. LPI Surebuttal of Lane Kollen 11-7-14, 52. DOC DER Revised Surrebuttal of Rakow 11-10-14, 53. DOC DER Revised Surrebuttal of Rakow-Redlined 11-10-14, 54. MP Supplemental Response to DOC IR 8 11-13-14, 55. MP Comments-Ambassador DOER to EPA 12-1-14, 56. MP FERC Order Exhibit 64 12-1-14, 57. Public Comments pt 1 of 7 12-4 2014, 58. Public Comments pt 2 of 7 12-4 2014, 59. Public Comments pt 3 of 7 12-4 2014, 60. Public Comments pt 4 of 7 12-4 2014, 61. Public Comments pt 5 of 7 12-4 2014, 62. Public Comments pt 6 of 7 12-4 2014, 63. Public Comments pt 7 of 7 12-4 2014, 64. Issues Matrix 12-5-14, 65. MP Brief & Proposed FOF all pts 12-19-14, 66. DOC DER Brief all pts 12-19-14, 67. RRANT Brief 12-19-14, 68. LPI Notice of Motion and Motion for Extensio of Time 12-22-14, 69. MP Reply Brief 1-16-15, 70. DOC DER Reply Brief 1-16-15, 71. DOC DER Reply Brief-Redlined Proposed Findings 1-16-15, 72. RRANT Reply Brief 1-16-15, 73. MP Letter to ALJ 2-3-15, 74. OAH Report and Recommendations 3-16-15, 75. LPI Exceptions to ALJ Report 3-31-15, 76. DOC DER Letter-Corrected 3-31-15, 77. DOC DER Reply Brief 1-16-15, 78. MP Exceptions to ALJ Report 3-31-15, 79. Briefing Papers, 80. MP Initial Filing pt 6 of 24 PUBLIC 10-21-13, 81. DOC Brief 12-19-14, 82. MP Direct Testimony of Michael Donahue 8-8-14 PUBLIC, 83. MP Direct Testimony of Allan Rudeck 8-8-14 PUBLIC, 84. LPI Testimony of Lane Kollen 9-19-14 PUBLIC, 85. MP Compliance 9-29-14 PUBLIC, 86. MP Surrebuttal Schedule 1 of Allan Rudeck 11-7-14 PUBLIC, 87. LPI Brief 12-22-14 PUBLIC, 88. LPI Reply Brief 1-16-15 PUBLIC
title
**      E015/CN-12-1163      Minnesota Power
In the Matter of the Application of Minnesota Power for a Certificate of Need for the 500 kilovolt Great Northern High-Voltage Transmission Line Project from the Manitoba, Canada - Minnesota Border to the Blackberry Substation near Grand Rapids, Minnesota.
 
Should the Commission adopt the Administrative Law Judge Report?
Do the Environmental Report and record of the Public Hearing address the items identified in the scoping decision?
Should the Commission grant a Certificate of Need for the proposed project?
If approved, should the Commission include any additional conditions? (PUC: Kaluzniak)