Title:
|
** E002/M-15-330; Northern States Power Company d/b/a Xcel Energy
E002/M-16-223
In the Matter of the Petition of Northern States Power Company d/b/a Xcel Energy for Approval of Cost Recovery of the Aurora PPA Pursuant to Minn. Stat. ? 216B.1645.
Should the Commission grant the petition for reconsideration of the Commission's April 13, 2016 Order Denying Recovery of the North Dakota-related Power Purchase Costs? (PUC: DeBleeckere)
The Commission has the authority to accept or decline a petition for reconsideration with or without a hearing or oral argument. (Minnesota Rules 7829.3000, Subpart 6) In other words, a decision on a petition for reconsideration can be made without taking oral comments at the Commission meeting.
|