File #: Details 2016-132    Version: Name:
Type: TL - Transmission Line Status: Agenda Ready
File created: 6/30/2016 In control: PUC Agenda Meeting
On agenda: 8/10/2017 Final action:
Title: * ET6/TL-16-327 Minnkota Power Cooperative In the Matter of the Application of Minnkota Power Cooperative, Inc. for a Route Permit for the MPL-Laporte 115 kV Transmission Line Project in Clearwater and Hubbard Counties, Minnesota. Should the Commission reconsider its June 21, 2017 Order Issuing Route Permit? (PUC: Panait) The Commission has the authority to accept or decline a petition for reconsideration with or without a hearing or oral argument (Minnesota Rules 7829.3000, Subpart 6). In other words, a decision on a petition for reconsideration can be made without taking oral comments at the Commission meeting.
Attachments: 1. `Order Issuing Route Permit 6-21-17, 2. Petition for Reconsideration (Seeger) 7-11-17, 3. Minnkota Response to Petition 7-21-17, 4. Briefing Papers

title

*                     ET6/TL-16-327                     Minnkota Power Cooperative

In the Matter of the Application of Minnkota Power Cooperative, Inc. for a Route Permit for the MPL-Laporte 115 kV Transmission Line Project in Clearwater and Hubbard Counties, Minnesota.

 

Should the Commission reconsider its June 21, 2017 Order Issuing Route Permit? (PUC: Panait)

 

The Commission has the authority to accept or decline a petition for reconsideration with or without a hearing or oral argument (Minnesota Rules 7829.3000, Subpart 6).  In other words, a decision on a petition for reconsideration can be made without taking oral comments at the Commission meeting.