Title:
|
** IP6946/TL-17-322 Freeborn Wind Energy LLC
In the Matter of the Application of Freeborn Wind Energy LLC for a Route Permit for the 161 kV Freeborn Wind Farm Transmission Line and Associated Facilities in Freeborn County.
1. What action(s) should the Commission take, if any, regarding the motions filed to the docket?
2. Should the Commission reconsider its December 19, 2018 Order Approving Route Permit for the Freeborn Wind Transmission Line Project? (PUC: Kaluzniak)
The Commission has the authority to accept or decline a petition for reconsideration with or without a hearing or oral argument (Minnesota Rules 7829.3000, Subpart 6) In other words, a decision on a petition for reconsideration can be made without taking oral comments at the Commission meeting.
|