title
** E015/AI-17-304 Minnesota Power
In the Matter of the Petition of Minnesota Power, an Operating Division of ALLETE, Inc., for Approval of Affiliated Interest Agreements Between ALLETE, Inc. and ALLETE Clean Energy, Inc.
1. Should the Commission approve the affiliated interest agreement to transfer the Bison 6 Large Generator Interconnection Agreement from ALLETE, Inc. to ALLETE Clean Energy, Inc.?
2. What date should be used to track depreciation, O&M, and tax expenses allocated to ALLETE Clean Energy, Inc.?
3. Should generation asset capital costs be included in the one-time payment from ALLETE Clean Energy, Inc.?
4. Does Minnesota Statute. § 216B.50 apply to any of the transactions in this proceeding? (PUC: Bartusch, Bonnett, Bender)