Details 2025-276
| 1 | 1. | | D - Depreciation | * E015/D-25-342 Minnesota Power
In the Matter of Minnesota Power’s Petition for Approval of 2025 Remaining Life Depreciation.
Should the Commission approve Minnesota Power’s 2025 Remaining Life Depreciation Proposal? (PUC: Pham) | |
Action details
|
|
Details 2023-141
| 1 | 2. | | CI - Commission Initiated Investigation | ** E999/CI-07-1199; All Electric Utilities
E999/DI-22-236;
E999/CI-14-643;
G008,G002,G11/
CI-23-117
G999/CI-21-565
In the Matter of Establishing an Estimate of the Costs of Future Carbon Dioxide Regulation on Electricity Generation Under Minnesota Statutes § 216H.06;
In the Matter of a Commission Investigation into Gas Utility Resource Planning;
In the Matter of a Commission Evaluation of Changes to Natural Gas Utility Regulatory and Policy Structures to Meet State Greenhouse Gas Reduction Goals.
What are the appropriate data sources and values for the regulatory cost of greenhouse gas emissions for Xcel Energy, CenterPoint Energy, and Minnesota Energy Resource Corporation’s upcoming gas integrated resource plans? (PUC: Dornfeld) | |
Action details
|
|
Details 2025-277
| 1 | 3. | | CN - Certificate of Need | ** ET2,E017,ET6135, Great River Energy;
E100/CN-24-263; Otter Tail Power Co.;
ET2,E017,ET6135, Western Minnesota Municipal Power Agency;
E100/TL-24-264 Agralite Electric Coop.;
City of Benson
In the Matter of the Application of Great River Energy, Otter Tail Power Co., Western Minnesota Municipal Power Agency, Agralite Electric Coop., and the City of Benson for a Certificate of Need and Route Permit for the Appleton to Benson 115-Kilovolt Transmission Line Project.
1. Should the Commission adopt the administrative law judge’s findings of fact, conclusions of law, and recommendation?
2. Should the Commission determine that the environmental assessment is adequate?
3. Should the Commission grant a certificate of need for the 115-kV Appleton to Benson Project?
4. Should the Commission grant a route permit for the 115 kV Appleton to Benson Project? (PUC: Lobby) | |
Action details
|
|
Details 2024-211
| 1 | 4. | | RP - Resource Planning | ** E002/RP-24-67; Northern States Power Co. d/b/a Xcel Energy
E002/CN-23-212
In the Matter of Northern States Power Co. d/b/a Xcel Energy 2024-2040 Integrated Resource Plan;
In the Matter of Xcel Energy’s Competitive Resource Acquisition Process for up to 800 Megawatts of Firm Dispatchable Generation.
1. Should the Commission approve the proposed Panamint - Cottage Grove BESS PPA?
2. Should the Commission authorize the Company to recover from Minnesota retail customers the Minnesota jurisdictional portion of the energy costs incurred under the PPA through the Fuel Clause Rider and capacity payments through base rates and the capacity tracker? (PUC: Stalpes) | |
Action details
|