| 1 | 1. | | CI - Commission Initiated Investigation | ** P421/CI-17-796 Qwest Corporation dba CenturyLink QC
In the Matter of a Commission Inquiry into CenturyLink’s Compliance with TAP Statutes and Rules.
1. Should the Commission grant CenturyLink’s petition for reconsideration?
2. Should the Commission take any other action? (PUC: Rebholz) | |
Action details
|
Details 2018-225
| 1 | 2. | | SA - Service Area | E249/SA-18-584 Hawley Public Utilities Commission;
Wild Rice Electric Cooperative
In the Matter of the Joint Request of Hawley Public Utilities Commission and Wild Rice Electric Cooperative for Approval of a Service Territory Transfer Agreement. (PUC: Terwilliger; DOC: Beckett) | |
Action details
|
Details 2017-202
| 3 | 3. | | CN - Certificate of Need | PULLED
** IP6984/CN-17-676 Flying Cow Wind, LLC
In the Matter of the Application of Flying Cow Wind, LLC for a Certificate of Need for the up to 152 MW Large Wind Energy Conversion System in Yellow Medicine County, Minnesota.
Should the Commission approve Flying Cow Wind, LLC’s request to withdraw its Application for a Certificate of Need under Minnesota Rule 7829.0430, Subpart 2? (PUC: Panait) | |
Action details
|
Details 2017-262
| 3 | 4. | | WS - Wind Power Plant Siting | * IP6984/WS-17-749 Flying Cow Wind, LLC
In the Matter of the Application of Flying Cow Wind, LLC for a Site Permit for the up to 152 MW Bitter Root Wind Project and Associated Facilities in Yellow Medicine County, Minnesota
1. Should the Commission adopt the administrative law judge’s Summary of Public Testimony, Findings of Fact, Conclusions of Law, and Recommendation?
2. Should the Commission grant a site permit for the up to 152 MW Bitter Root Wind Large Wind Energy Conversion System in Yellow Medicine County? (PUC: Panait) | |
Action details
|
Details 2018-224
| 1 | 5. | | CI - Commission Initiated Investigation | ** E002/CI-17-401 Northern States Power Company d/b/a Xcel Energy
In the Matter of the Commission Investigation to Identify and Develop Performance Metrics and, Potentially, Incentives for Xcel Energy’s Electric Utility Operations.
What action should the Commission take on performance-based ratemaking for Xcel Energy (Xcel or the Company), including Xcel’s 2021 and 2022 Performance-Based Ratemaking Annual Reports (PBR Reports)? (PUC: Dornfeld, Terwilliger) | |
Action details
|