Details 2021-145
| 1 | 1. | | M - Miscellaneous | * E111/M-21-45 Dakota Electric Association
In the Matter of the Petition by Dakota Electric Association for Approval of Monthly Fixed Charges per Meter for the Advanced Grid Infrastructure (AGi) Rider.
Should the Commission approve Dakota Electric Association’s 2021 AGi Rider Monthly Fixed Charge per Meter amounts for various rate classes? (PUC: McShane) | |
Action details
|
Details 2021-161
| 1 | 2. | | M - Miscellaneous | ** P421/M-21-381 CenturyLink QC
In the Matter of a Petition for a Rulemaking Regarding Minnesota Rules Chapter 7810.
Should the Commission open a Rulemaking proceeding to modify or eliminate portions of Minnesota’s Telephone Quality of Service Rules? (PUC: O’Grady) | |
Action details
|
Details 2021-146
| 1 | 3. | | WS - Wind Power Plant Siting | * IP6646/WS-09-584 Xcel Energy
In the Matter of Site Permit Amendment Application for Proposed Upgrades to Xcel Energy’s Nobles Wind Farm in Nobles County, Minnesota.
Should the Commission approve the requested amendments to the Nobles Wind Farm LWECS site permit? (PUC: Bruce) | |
Action details
|
Details 2019-219
| 3 | 4. | | CN - Certificate of Need | IP6997/CN-18-699; Plum Creek Wind Farm, LLC
IP6997/WS-18-700;
IP6997/TL-18-701
In the Matter of the Applications of Plum Creek Wind Farm, LLC for a certificate of Need, Site Permit, and Route Permit for an up to 414 MW Large Wind Energy Conversion System and 345 kV Transmission Line in Cottonwood, Murray, and Redwood Counties.
1. Should the Commission approve Plum Creek’s request to amend the Certificate of Need for the Plum Creek Project?
2. Should the Commission approve Plum Creek’s request to amend the site permit for the Plum Creek Project?
3. Should the Commission approve Plum Creek’s request to amend the route permit for the Plum creek Wind Project?
4. If the amendments are authorized, what additional conditions, if any, should the Commission impose? (PUC: Harvieux; DOC: Steinhauer) | |
Action details
|