Details 2025-074
| 1 | 1. | | M - Miscellaneous | ** E002,PT7157/ City of Slayton;
SA-25-129 Northern States Power Co.
d/b/a Xcel Energy
In the Matter of the Petition of the City of Slayton for the Determination of Compensation for City Acquisition of Xcel Energy Electric Service Territory.
Should the Commission refer this case to the OAH for a contested case to determine just compensation under Minnesota Statutes, Section 216B.45, or adopt some other procedure? (PUC: Noyce) | |
Not available
|
Details 2025-075
| 1 | 2. | | M - Miscellaneous | * ?G004/M-24-234 Great Plains Natural Gas Co.
In the Matter of ?Great Plains Natural Gas Co.’s Petition for Approval of changes in Contract Demand Entitlements for the 2024-2025 Winter Heating Season?.
Should the Commission approve Great Plains’ proposed demand entitlement levels and cost changes? (PUC: Pham) | |
Not available
|
Details 2025-058
| 1 | 3. | | M - Miscellaneous | ** E017/M-24-204 Otter Tail Power Co.
In the Matter of Otter Tail Power Co.'s Petition for Approval of the Annual Rate Update to its Transmission Cost Recovery Rider Annual Adjustment.
1. Should the Commission approve Otter Tail Power Co.’s 9th annual rate update to its Transmission Cost Recovery Rider (TCRR)?
2. Should the Commission determine Otter Tail Power Co.’s Milbank Area Reliability project is eligible for recovery through the TCRR under Minn. Stat. § 216B.16, subd. 7b? (PUC: Ubani) | |
Not available
|
Details 2023-174
| 1 | 4. | | M - Miscellaneous | ** E017/M-23-261 Otter Tail Power Co.
In the Matter of Otter Tail Power Co.’s Proposal for A Residential Time of Day Pilot Plan.
Should the Commission approve Otter Tail Power Co.’s petition for a Residential Time of Day Pilot Plan as found in its September 20, 2004 compliance filing? (PUC: Gomez) | |
Not available
|
Details 2024-107
| 1 | 5. | | M - Miscellaneous | ** E015/M-23-258 Minnesota Power
In the Matter of Minnesota Power’s 2023 Integrated Distribution Plan.
Should the Commission approve, modify, or reject Minnesota Power’s multi-dwelling unit EV charging pilot program? (PUC: Noyce) | |
Not available
|