Details 2013-143
| 4 | 1. | | R - Rulemaking | * U999/R-13-24 All Utilities
In the Matter of Possible Amendments to Rules Governing Utility Proceeding, Practice, and Procedure, Minnesota Rules Chapter 7829, Excluding Part 7829.2550, Which is Subject to a Separate Pending Rulemaking.
Should the Commission Adopt Rule Revisions Recommended by the ALJ? (PUC: Moseng) | |
Action details
|
|
13-114
| 3 | 2. | | M - Miscellaneous | *** E,G002/CI-02-2034; Northern States Power Co. d/b/a Xcel Energy
E,G002/M-12-383
In the Matter of an Investigation & Audit of Service Quality Reporting - Fraudwise Report;
In the Matter of the Petition of Northern States Power Company d/b/a Xcel Energy for Approval of Amendments to its Natural Gas and Electric Service Quality Tariffs Originally Established in Docket No. E, G-002/CI-02-2034.
1. Should the Commission accept Xcel Energy’s Annual 2024 Quality of Service (QSP) Report?
2. Should the Commission approve Xcel Energy’s proposal to use 50% of the Customer Complaint under performance penalty for bill credits to past due customers?
3. Should the Commission approve Xcel Energy’s proposal to use 50% of the Telephone Response Time under performance penalty for deployment of its Live Chat function?
4. Are there other issues or concerns related to this matter? (PUC: McShane) | |
Action details
|
|
Details 2015-085
| 2 | 3. | | CN - Certificate of Need | *a ET2,E015/CN-14-853 Great River Energy;
Minnesota Power
In the Matter of the Joint Application of Great River Energy and Minnesota Power for a Certificate of Need and Route Permit for the Motley Area 115 KV Transmission Line Project in Morrison, Cass, and Todd Counties.
Should the Commission find that the Environmental Report/Assessment on this project is complete and addresses the Scoping Decision of the Department of Commerce? Should the Commission grant a Certificate of Need for the proposed 115 kV transmission line project? (PUC: DeBleeckere)
b ET2/E015/TL-15-204 Great River Energy;
Minnesota Power
In the Matter of the Joint Application of Great River Energy and Minnesota Power for a Route Permit for the Motley Area 115 kV Transmission Line Project in Morrison, Cass and Todd Counties.
Should the Commission find that the Environmental Assessment and the record on this project adequately address the issues identified in the Scoping Decision? Should the Commission issue a route permit identifying a specific route and permit conditions for the proposed 115 kV | |
Action details
|