Details 2026-031
| 1 | 1. | | M - Miscellaneous | * E015/M-24-382 Minnesota Power
In the Matter of Minnesota Power’s Petition for Approval of its 2025 Rate Adjustment Mechanism (2025 Transmission Factor) under its Rider for Transmission Cost Recovery (TCR or Rider).
Should the Commission approve Minnesota Power’s request for its 2025 rate adjustment mechanism under its Rider for Transmission Cost Recovery? (PUC: Worlobah) | |
Not available
|
|
Details 2026-032
| 1 | 2. | | M - Miscellaneous | * E002/M-25-386 Northern States Power Co. d/b/a Xcel Energy
In the Matter of Xcel Energy’s Petition for approval of 2026 Transmission Cost Recovery (TCR) Rider revenue requirements and the resulting adjustment factors by customer class.
Should the Commission provisionally approve Xcel Energy’s TCR rate effective January 1, 2026, subject to final review? (PUC: Willette) | |
Not available
|
|
Details 2025-061
| 2 | 3. | | M - Miscellaneous | ** IP7155/ESS-25-123 North Star Energy Storage, LLC
In the Matter of the Application of North Star Energy Storage, LLC for an up to 80-megawatt Battery Energy Storage System Site Permit for the North Star Storage Project in Chisago County, Minnesota.
1. Should the Commission adopt the administrative law judge’s findings of fact, conclusions of law, and recommendation?
2. Should the Commission determine that the environmental assessment and the record created at the public hearing adequately address the issues identified in the scoping decision?
3. Should the Commission grant a site permit for the up-to-100-megawatt North Star Battery Energy Storage System Project in Chisago County? (PUC: Ek) | |
Not available
|
|
Details 2024-211
| 1 | 4. | | RP - Resource Planning | ** E002/RP-24-67; Northern States Power Co. d/b/a Xcel Energy
E002/CN-23-212
In the Matter of Northern States Power Co. d/b/a Xcel Energy 2024-2040 Integrated Resource Plan;
In the Matter of Xcel Energy’s Competitive Resource Acquisition Process for up to 800 Megawatts of Firm Dispatchable Generation.
1. Should the Commission approve the proposed Panamint - Cottage Grove BESS PPA?
2. Should the Commission authorize the Company to recover from Minnesota retail customers the Minnesota jurisdictional portion of the energy costs incurred under the PPA through the Fuel Clause Rider and capacity payments through base rates and the capacity tracker? (PUC: Stalpes) | |
Not available
|
|
Details 2026-013
| 1 | 5. | | AI - Affiliated Interest | ** E002/AI-25-245 Northern States Power Co. d/b/a Xcel Energy
In the Matter of Xcel Energy’s Petition for Approval of its 2025 Annual Administrative Service Agreement.
Should the Commission approve Xcel Energy’s 2025 Annual Administrative Service Agreement Petition? (PUC: Pham) | |
Not available
|