Details 2021-310
| 2 | 1. | | TL - Transmission Line | * E015/TL-21-141 Minnesota Power
In the Matter of the Application of Minnesota Power for a Route Permit for the Duluth Loop Reliability Project in Saint Louis County, Minnesota.
What action should the Commission take regarding route alternatives to be evaluated in the environmental assessment? (PUC: Panait) | |
Action details
|
Details 2017-152
| 16 | 2. | | WS - Wind Power Plant Siting | ** IP6946/WS-17-410 Xcel Energy
In the Matter of the Energy Conversion System Site Permit for the 84 MW Freeborn Wind Farm in Freeborn County.
Should the Commission reconsider its August 8, 2022 Order Accepting Post Construction Noise Monitoring Report and Compliance Review? (PUC: Kaluzniak)
The Commission has the authority to accept or decline a petition for reconsideration with or without a hearing or oral argument (Minnesota Rules 7829.3000, Subpart 6) In other words, a decision on a petition for reconsideration can be made without taking oral comments at the Commission meeting. | |
Action details
|
Details 2021-306
| 2 | 3. | | M - Miscellaneous | ** E002/M-21-590 Northern States Power Co. d/b/a Xcel Energy
In the Matter of Xcel Energy’s Petition for Approval of a Power Purchase Agreement (PPA) between Northern States Power Company and St. Paul Cogeneration, LLC (SPC).
Should the Commission approve Xcel’s proposed electrification project and the requested Power Purchase Agreement extension? (PUC: Zhang) | |
Action details
|