Details 2015-026
| 1 | 1. | | NA - New Authority | * P6939/NA-14-959 CenturyLink Public Communications, Inc.
Application of CenturyLink Public Communications, Inc. for a Certificate of Authority to Provide Facilities-based Competitive Local Exchange Service Limited to the provision of Inmate Calling Services. (PUC: Oberlander; DOC: Doherty) NOTE: Staff supports the Department’s recommendation to grant authority with conditions. | |
Action details
|
Details 2014-106
| 2 | 2. | | PR - Periodic Reports | * P999/PR-14-15 All Telecommunications Service Providers
In the Matter of Intercarrier Compensation Reform Required by FCC Order. (PUC: O’Grady; DOC: Linscheid, Doherty) NOTE: Staff supports the Department’s conclusion and recommendation to close this docket. | |
Action details
|
Details 2014-253
| 2 | 3. | | AR - Alternative Regulation | * P405/AR-14-735 Frontier Communications of Minnesota, Inc.
In the Matter of a Petition by Frontier Communications of Minnesota, Inc. for Approval of its Revised Alternative Regulation (AFOR) Plan.
Should the Commission approve Frontier's Revised Alternative Regulation Plan as filed as a settlement between Frontier and the Department on January 8, 2015? (PUC: McCarthy) | |
Action details
|
Details 2015-022
| 1 | 4. | | D - Depreciation | ** E,G002/D-15-46 Northern States Power Company d/b/a Xcel Energy
In the Matter of Northern States Power Company's Request for Approval of the Annual Review of Remaining Lives Depreciation for Electric and Gas Production and Gas Storage Facilities and Net Salvage Rates for 2015.
Should the Commission approve the proposed depreciation rates?
Should the Commission approve the proposed modification of the lives of certain plants?
Should the Commission approve the proposed reallocation of depreciation reserves? (PUC: Dasinger, Schwieger) | |
Action details
|
Details 2015-027
| 1 | 5. | | M - Miscellaneous | * E017/M-14-375 Otter Tail Power Company
In the matter of Otter Tail Power’s Petition for Approval of a Transmission Cost Recovery Rider under Minn. Stat. § 216B.16, subd. 7b.
Should the proposed increases to the charges under the Transmission Cost Recovery Rider be approved by the Commission? (PUC:Schwieger) | |
Action details
|
Details 2015-023
| 1 | 6. | | M - Miscellaneous | ** E002/M-14-162 Northern States Power Company d/b/a Xcel Energy
In the Matter of Petition for Approval of a Solar Portfolio to Meet Initial Solar Energy Standard.
Should the Commission approve Xcel Energy's October 24, 2014 Petition for Approval of three solar Purchase Power Agreements?
Should the Commission approve Xcel Energy's Revised Request for approval of two solar Purchase Power Agreements, as described in the Company's reply comments?
What other actions should the Commission take in this proceeding? (PUC: Stalpes, Twite, DeBleeckere. Mackenzie) | |
Action details
|