Details 2020-196
| 5 | 1. | | M - Miscellaneous | ** E002/M-20-620 Northern States Power Company, d/b/a Xcel Energy
In the Matter of a Petition from Northern States Power Company, d/b/a/ Xcel Energy, for Approval of Updated Pricing for the Border Winds and Pleasant Valley Wind Repowering Projects.
1. Should the Commission approve capital costs higher than previously-approved in this proceeding for the Border Winds and Pleasant Valley wind repowering projects?
2. Should the Commission continue to allow Xcel Energy to pursue cost recovery of the Border Winds and Pleasant Valley wind projects in a future Renewable Energy Standard Rider filing?
3. Should the Commission require Xcel to refund ratepayers if wind production tax credits (PTCs) are less than what the Company assumed in its October 14, 2022, Pricing Update? (PUC: Stalpes) | |
Action details
|
Details 2021-118
| 2 | 2. | | CI - Commission Initiated Investigation | P999/CI-20-747 All High Cost ETCs
In the Matter of a Commission Inquiry into the Advertising, Outreach, and Offering of Lifeline by High Cost ETCs.
What actions should the Commission take in response to the filings submitted by high-cost Eligible Telecommunications Carriers (ETCs) in compliance with the Commission’s July 20, 2021 Order in the current docket? (PUC: McShane; DOC: Dietz) | |
Action details
|
Details 2023-020
| 1 | 3. | | PR - Periodic Reports | * E999/PR-22-12; All Electric Utilities Subject to Minnesota
E999/M-22-85; Statute §216B.1691
E999/PR-02-1240
In the Matter of Commission Consideration and Determination of Compliance with Renewable Energy Standards for Year 2021;
In the Matter of Commission Consideration and Determination of Compliance with Renewable Energy Standards Biennial Reporting;
In the Matter of Green Pricing Verification Filing Process.
1. What action should the Commission take on the Renewable Energy Standards (RES) compliance filings filed by electric utilities for compliance year 2021?
2. What action should the Commission take regarding Otter Tail Power’s proposal? (PUC: Harsch) | |
Action details
|
Details 2016-131
| 11 | 4. | | M - Miscellaneous | ** E002/M-13-867 Northern States Power Co. d/b/a Xcel Energy
In the Matter of the Petition of Northern States Power Co. d/b/a Xcel Energy for Approval of its Proposed Community Solar Garden Program
Was Xcel Energy’s Applicable Retail Rate (ARR) Compliance filing on July 31, 2024 properly filed by the process established in the July 22, 2022 Commission order? (PUC: Brown-Huss) | |
Action details
|
Details 2018-089
| 2 | 5. | | CI - Commission Initiated Investigation | ** E999/CI-16-521 All Electric Utilities
In the Matter of Updating the Generic Standards for the Interconnection and Operation of Distributed Generation Facilities Established Under Minn. Stat. §216B.1611.
What changes to the Minnesota Distributed Energy Resources Interconnection Process (MN DIP) should the Commission make to achieve the purpose of Minnesota Law 2023, Ch. 60, Art. 12, Sec. 75 (HF 2310)? (PUC: Duran) | |
Action details
|