Details 2013-322
| 1 | 1. | | TL - Transmission Line | * E015/TL-13-805 Minnesota Power
In the Matter of the Application of Minnesota Power for a Route Permit for the Canisteo 115 Kilovolt High Voltage Transmission Line Project in Itasca County.
Should the Commission find that the environmental assessment and the record created at the public hearing adequately address the issues identified in the scoping decision? Should the Commission adopt the Administrative Law Judge Report? Should the Commission issue a route permit identifying a specific route and permit conditions for the Canisteo 115 Kilovolt High Voltage Transmission Line (HVTL) Project in Itasca County? (PUC: Kaluzniak) | |
Action details
|
Details 2014-006
| 1 | 2. | | CN - Certificate of Need | * IP6828/CN-09-937 Pleasant Valley Wind, LLC
In the Matter of the Application of Pleasant Valley Wind, LLC for a Certificate of Need for up to 301 MW at the Pleasant Valley Project in Dodge and Mower Counties in Southeastern Minnesota.
Should the Commission amend Pleasant Valley Wind LLC’s certificate of need to specify a reduced nameplate capacity for the project? (PUC: Ek) | |
Action details
|
Details 2014-007
| 1 | 3. | | WS - Wind Power Plant Siting | ** IP6828/WS-09-1197 Northern States Power Company d/b/a Xcel Energy
In the Matter of the Application for an Amendment to the Site Permit to Repower the 200 MW Pleasant Valley Wind Project in Dodge and Mower Counties, Minnesota.
Should the Commission approve the requested amendments to the Pleasant Valley Wind Farm site permit? (PUC: Janezich) | |
Action details
|
Details 2014-008
| 1 | 4. | | M - Miscellaneous | E015/M-13-1084 Minnesota Power
Minnesota Power’s Petition for Approval of an Amendment to the Electric Service Agreement Between Boise, Inc. and Minnesota Power. (PUC: Kaml; DOC: Zajicek) NOTE: Staff agrees with the recommendations of the Department of Commerce. | |
Action details
|
Details 2014-009
| 1 | 5. | | AI - Affiliated Interest | E015/AI-13-966 Minnesota Power
Minnesota Power’s Petition for Approval of An Affiliated Interest Agreement with Superior Water, Light and Power Company. (PUC: Kaml; DOC: Addonizio) NOTE: Staff agrees with the recommendations of the Department of Commerce. | |
Action details
|
Details 2014-010
| 1 | 6. | | M - Miscellaneous | * G001/M-13-579 Interstate Power and Light Company (IPL)
In the Matter of lPL's Request for Changes in Demand Entitlements.
Should the Commission approve IPL’s proposed level of demand entitlement effective November 1, 2013 and allow IPL to recover the associated demand costs through the monthly Purchased Gas Adjustment? (PUC: Bender) | |
Action details
|
Details 2014-002
| 2 | 7. | | M - Miscellaneous | * E017/M-13-103 Otter Tail Power Company
In the Matter of Otter Tail Power Company’s Request for Approval of a Transmission Cost Recovery Rider Including the Proposed Transmission Factor for the Recovery Period from May 2, 2013 to April 30, 2014.
Should the Commission approve Otter Tail Power’s request to keep the current rates in its Transmission Cost Recovery Rider or require the Company to implement new rates in the Rider? (PUC: Schweiger, Dasinger) | |
Action details
|