Details 2015-046
| 4 | 1. | | CN - Certificate of Need | ** ET2,E015/CN-14-787; Great River Energy;
ET2,E015/TL-14-797 Minnesota Power
In the Matter of the Joint Applications of Great River Energy and Minnesota Power for a Certificate of Need and a Route Permit for the Menahga Area 115 kV Transmission Line Project in Hubbard, Wadena and Becker Counties.
· Should the Commission find that the environmental assessment is adequate?
· Should the Commission adopt the applicants’ proposed findings and conclusions and also suggested permit revisions?
· Should the Commission grant a certificate of need for the Menahga Area 115 kV Transmission Line Project?
· Should the Commission issue a route permit identifying a specific route and permit conditions for the Menahga Area 115 kV Transmission Line Project? (PUC: Panait) | |
Action details
|
Details 2016-002
| 1 | 2. | | S - Securities | * G022/S-15-956 Greater Minnesota Gas, Inc. (GMG)
In the Matter of the Petition of Greater Minnesota Gas, Inc. for Approval of 2016 Capital Structure and Permission to Issue Securities.
Should the Commission adopt the Department’s recommendation to modify GMG’s petition for approval of capital structure and permission to issue securities? (PUC: Krishnan, Kaml) | |
Action details
|
Details 2016-005
| 1 | 3. | | M - Miscellaneous | * E015/M-15-699 Minnesota Power
In the Matter of Minnesota Power’s Petition for Approval of an Electric Service Agreement between Magnetation, LLC and Minnesota Power
Should the Commission approve Minnesota Power’s Electric Service Agreement with Magnetation? (PUC: Kaml, Krishnan) | |
Action details
|
Details 2016-006
| 1 | 4. | | M - Miscellaneous | * E015/M-15-1000 Minnesota Power
In the Matter of the Petition of Minnesota Power for Approval of an Amended and Restated Electric Service Agreement Between ArcelorMittal Minorca Mine Inc. and Minnesota Power (PUC: Krishnan; DOC: Wils) | |
Action details
|
Details 2016-001
| 1 | 5. | | M - Miscellaneous | ** E015/M-15-773 Minnesota Power
In the Matter of the Petition of Minnesota Power for Approval of Investments and Expenditures in the Camp Ripley Solar Project for Recovery through Minnesota Power’s Renewable Resources Rider under Minn. Stat. § 216B.1645 and Related Tariff Modifications.
Should the Commission approve Minnesota Power’s compliance filing, including the initial cost recovery amount for its land lease and proposal to adjust its Fuel and Purchased Energy (FPE) and Solar Energy Adjustment (SEA) Riders? (PUC: Mackenzie) | |
Action details
|