Details 2022-029
| 1 | 1. | | RV - Revocation Investigation | * P6692/RV-21-425 Total Holdings, Inc, dba GTC Communications
In the Matter of the Revocation of Total Holdings, Inc, dba GTC Communications Certificate of Authority. (PUC: Fournier; DOC: Gonzalez) | |
Action details
|
Details 2022-032
| 1 | 2. | | M - Miscellaneous | ** E002/M-20-815 Northern States Power Company, d/b/a Xcel Energy
In the Matter of Northern States Power Company d/b/a Xcel Energy’s Petition for Approval of the Renewable Energy Standard Rider Revenue Requirements for 2021 and Revised Adjustment Factors.
1. Should the Commission approve or modify Xcel Energy’s RES rider revenue requirement for 2021 and the accompanying revised RES adjustment factors?
2. Should the Commission alter Xcel Energy’s REC management strategy including its Certified Renewable Percentage (CRP) Program? (PUC: Gustafson, Ubani) | |
Action details
|
Details 2022-033
| 1 | 3. | | M - Miscellaneous | ** E015/M-20-900 Minnesota Power
In the Matter of Minnesota Power’s Request for Approval of its 2021 Transmission Factors under its Transmission Cost Recovery Rider.
Should the proposed charges under the Transmission Cost Recovery Rider be approved? (PUC: Manning) | |
Action details
|
Details 2021-054
| 2 | 4. | | CN - Certificate of Need | * IP7039/CN-20-646; Louise Solar Project, LLC
IP7039/GS-20-647
In the Matter of the Applications of Louise Solar Project, LLC for a Certificate of Need for the 50 MW Louise Solar Project in Mower County, Minnesota;
In the Matter of the Applications of Louise Solar Project, LLC for a Site Permit for the 50 MW Louise Solar Project in Mower County, Minnesota.
1. Should the Commission find that the environmental assessment and the record created at the public hearing adequately address the issues identified in the scoping decision?
2. Should the Commission grant a certificate of need for the 50- megawatt Louise Solar Project?
3. Should the Commission adopt the administrative law judge’s Findings of Fact, Conclusions of Law, and Recommendation?
4. Should the Commission grant a site permit for the 50-megawatt Louise Solar Project? (PUC: Panait) | |
Action details
|
Details 2021-105
| 3 | 5. | | WS - Wind Power Plant Siting | * IP7046/WS-20-860 Northern Wind Energy Redevelopment, LLC
In the Matter of the Request for Partial Transfer of the Site Permit for the up to 122.3-megawatt Northern Wind Large Wind Energy Conversion System in Murray County, Minnesota.
1. Should the Commission authorize a partial transfer of the site permit?
2. If a partial permit transfer is authorized by the Commission, what amendments to te site permit are necessary? (PUC: Ek) | |
Action details
|
Details 2022-030
| 1 | 3. | | PA - Property Acquisition | P6854,6082/PA-22-49 BBY Networks, Inc.;
Zayo Group, LLC
In the Matter of a Petition by BBY Networks, Inc. and Zayo Group, LLC for Approval of a Change in Control. (PUC: Fournier; DOC: Dietz) | |
Action details
|
Details 2022-031
| 1 | 4. | | RP - Resource Planning | ET10/RP-21-414 Missouri River Energy Services
In the Matter of Missouri River Energy Services 2022-2036 Integrated Resource Plan. (PUC: Bahn; DOC: Davis) | |