Title:
|
** G008/GR-17-285 CenterPoint Energy Resources Corp., d/b/a
CenterPoint Energy Minnesota Gas
In the Matter of the Application by CenterPoint Energy for Authority to Increase Natural Gas Rates in Minnesota.
1. Should the Commission accept CenterPoint Energy's revised annual Short-Term Incentive Compensation Plan Report for 2019?
2. Should the Commission require a refund to ratepayers, and, if so, should the Commission require a refund of $52,994 or $147,212, plus interest?
3. Should the Commission allow CenterPoint Energy to combine any incentive compensation refund required with its interim rate refund in docket G-008/GR-19-524? (PUC: Bender)
|